After considering the queries, clarifications, recommendations and suggestions, the BAC4IGOV hereby decides to include, revise, amend, delete and/or adapt the following provisions:

Lot 1: Supply and Delivery of Layer 3 Aggregation Routers
Technical Specification
Original Provision Amended Provision
2.2   8-GB ECC-protected DRAM 2.2    6-GB ECC-protected DRAM
2.5   Ports:  4 x 10 GE SFP+, 20 x 1 GE SFP 2.5 Ports: 4 x 10 GE SFP+, 20 x 1 GE SFP, included transceivers 4x10GESFP+LR and 10 x 1GE SFP LX/LH
2.7   Standard 2.7    Compliance
3.     Integrated Service Module Line Card. Must provide a highly scalable modular services delivery platform for delivering multiple types of services such as CGN, Dual-lite and NAT64

 

Including items 3.1 up to 3.9

 

These items have been deleted.

 

Item number 4 up to 4.10.13 has been renumbered. New numbering is 3 up to 3.10.13
Lot 2: Supply and Delivery of 8 Port GigE POE Switch with Fiber Optic Transceiver
Ports

2 SFP port; include two SFP 1000Base LH transceiver module and two single-mode LC to LC patch cords (3 meters)

Ports

2 SFP port; include two SFP 1000Base LX transceiver module and two single-mode LC to LC patch cords (3 meters)

PoE capability

67 W PoE

PoE capability

60 W PoE

Warranty: 3 years warranty with 24×7 coverage for hardware Warranty: 1 year warranty with 24×7 coverage for hardware

 

Further, relation to the queries, clarifications, recommendations and suggestions for the aforementioned project, hereunder is the official response of the BAC4IGOV:

Item Queries BAC4IGOV Responses
Technical Specifications
Ports: 4 x 10 GE SFP+, 20 x 1 GE SFP Does it include transceivers? Yes, transceivers are included.
Integrated Service Module Line Card

 

Must provide a highly scalable modular service delivery platform for delivery multiple types of services such as CGN, Dual-lite and NAT64

Will this be used as a spare? Requirement is 2RU only and it will need 6RU to insert the ISML Card ISM Card requirement was removed.
SFP port; include two FP 1000Base LH Transceiver module and two single-mode LC to LC patch cords (3 meters) Please verify fiber distance required for LH single-mode transceiver connectivity. If you require less than 10km using single-mode fiber, then we can offer 1G-LX transceivers 1G LX is ok.
Must be compatible with the existing configuration What is the existing configuration? Existing configuration utilizes extreme switches configured to use ospf and mpls as Layer3 protocols to enable l2vpn services between any two points inside the network.
Section III Bid Data Sheet (BDS) Clause 20.3

 

Each Bidder shall submit the following in one (1) big envelope duly labeled containing two sets of envelopes

If we will bid for this Items No. 1 & 2, do we need to submit two (2) big envelopes which will contain two (2) separate sets of Eligibility and Technical Documents/Financial Documents? Or one (1) set of Eligibility and Financial will suffice for the bid of 2 lots? There is no need to submit two (2) big envelopes.  If you are bidding for two lots, one set of eligibility and financial documents will suffice.

All terms, conditions and instructions to bidders specified in the Bidding Documents inconsistent with this Bid Bulletin are hereby superseded and modified accordingly.

Please use the following forms attached in this Supplemental Bid Bulletin:

  • Revised Technical Specifications as of 29 October 2015 (Lot 1: SUPPLY AND DELIVERY OF LAYER 3 AGGREGATION ROUTERS)
  • Revised Technical Specifications as of 29 October 2015 (Lot 2: 8 port GigE POE Switch with Fiber Optic Transceivers)
  • Revised Checklist of Requirements for Bidders as of 29 October 2015.

 

For a copy of the complete document including Revised Technical Specifications, kindly click on the link below:
Supplemental Bid Bulletin No. 1 – Supply and Delivery of Various Network Equipment

For information and guidance of all concerned.

Issued this 29th day of October 2015.

 

 

(SGD.) DENIS F. VILLORENTE

Chairman, BAC4IGOV