After considering the queries, clarifications, recommendations and suggestions made the BAC4IGOV hereby decides to include, revise, amend, delete and/or adapt certain provisions.

Please be advised of the changes in the schedule of the Bid Opening and Bid Submission:

Activity Previous Schedule Revised Schedule
Bid Submission 4 August 2015, 10:00 AM 4 August 2015, 12 Noon
Bid Opening 4 August 2015, 10:15 AM 4 August 2015, 3 PM

In the Terms of Reference of the aforementioned project, the provisions for the following have been amended:

1. Tuguegarao FOC Network
2. San Fernando Pampanga FOC Network
3. Item 3.2 – Warehouse (To be provided by ICTO)
4. Section V – Special Conditions of the Contract (SCC), GCG Clause 10
5. Section 3, Bid Data Sheet, ITB clause 13.1

Please use the Revised Technical Specifications, Revised Annex VII-A, Revised Annex VIII-A, Revised Annex VIII-B, and Revised Checklist of Requirements for attached in this Supplemental Bid Bulletin.

All terms, conditions and instructions to bidders specified in the Bidding Documents inconsistent with this Bid Bulletin are hereby superseded and modified accordingly.

To download this document, click on the link below:

Supplemental Bid Bulletin No. 2 – Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning, Operation and Maintenance of Brand New Fiber Optic cable in Three (3) Regional Government Centers

For information and guidance of all concerned.

 

(SGD)DENIS F. VILLORENTE
Chairman, BAC4iGOV