In relation to the Supplemental Bid Bulletin 1 and 2 the BAC4IGOV hereby decides to to include, revise, amend, delete and/or adapt certain provisions.

In the Revised Technical Specification, item 1.2.1 which states, “2 units Photoelectric Smoke and Ionization Detector” is amended to read as follows:

“2 units Photoelectric Smoke Detector

Further, that in Section VI (Schedule of Requirements), Schedule of Requirements is amended to read as follows:

“Schedule of Requirements

The delivery schedule of service shall be completed within forty-five (45) calendar days from issuance of Notice to Proceed.

Description Qty ICT Office ABC Delivered, Weeks / Months
Supply, Delivery, Installation, Testing and
Commissioning of Fire Detection and
Suppression System at the Battery Room
1 Lot P1,280,000.00 Forty-Five (45) calendar days from issuance of Notice to Proceed

Provided further, that in Annex V, Technical Bid Form is also modified. Please use the Revised Technical Specification, Revised Schedule of Requirements, Revised Annex V, and Revised Checklist of Requirements attached in this Supplemental Bid Bulletin.

All terms, conditions and instructions to bidders specified in the Bidding Documents inconsistent with this Bid Bulletin are hereby superseded and modified accordingly.

To download this supplemental bid bulletin with the Annex V, click on the link below:

Supplemental Bid Bulletin No. 3 – Supply, Delivery, Installation, Testing and Commissioning of Fire Detection and Suppression System at the Battery Room

For information and guidance of all concerned.

(SGD.) DENIS F. VILLORENTE
Chairman, BAC4iGOV