BIDS AND AWARDS COMMITTEE
Supplemental Bid Bulletin No. 2
ONE (1) YEAR MAINTENANCE OF DICT-FIBER OPTIC CABLE (FOC) NETWORK IN SAN FERNANDO CITY, PAMPANGA INCLUDING SUPPLY AND DELIVERY OF FOC NETWORK
Bid Reference No. BAC4G&S-2018-014
Please be advised of the changes in the schedule of the Submission and Opening of Bids for this project:
ACTIVITY | PREVIOUS SCHEDULE | REVISED SCHEDULE |
Submission of Bids | 15 October 2018
12 Noon |
19 October 2018
12 Noon |
Opening of Bids | 15 October 2018
1:30PM |
19 October 2018
1:30PM |
ORIGINAL PROVISION | AMENDED PROVISION |
Section I. Invitation to Bid | |
4) A prospective Bidder should have completed within the last five (5) years from the date of submission and receipt of bids at least one (1) single contract of similar nature amounting to at least fifty percent (50%) of the ABC.
For this project, “similar in nature” shall mean “Direct experience on planning, engineering, supply and delivery, installation, testing and commissioning and experience in operations and maintenance of optical fiber distribution and transmission projects/systems”. |
4) A prospective Bidder should have completed within the last five (5) years from the date of submission and receipt of bids at least one (1) single contract of similar nature amounting to at least fifty percent (50%) of the ABC.
For this project, “similar in nature” shall mean “ Installation of Optic Fiber Cable Network” |
Section III. Bid Data Sheet | |
5.4) The Bidder must have completed, within last five (5) years from the date of submission and receipt of at least one (1) single contract of similar nature amounting to at least fifty percent (50%) of the ABC
For this project, “similar in nature” shall mean “Direct experience on planning, engineering, supply and delivery, installation, testing and commissioning and experience in operations and maintenance of optical fiber distribution and transmission projects/systems”. |
5.4) The Bidder must have completed, within last five (5) years from the date of submission and receipt of at least one (1) single contract of similar nature amounting to at least fifty percent (50%) of the ABC
For this project, “similar in nature” shall mean “Installation of Optic Fiber Cable Network”
|
All terms, conditions and instructions to bidders specified in the Bidding Documents inconsistent with this Bid Bulletin are hereby superseded and modified accordingly.
For information and guidance of all concerned.For a full copy of the document, Click the link below:
Issued this 9th day of October 2018.
(Original Signed)
JIEZL GABRIELLE G. REOTURAR
Vice Chairperson, BAC4G&S