Please be advised of the changes in the schedule of the Bid Submission and Bid Opening for this project:
ACTIVITY | PREVIOUS SCHEDULE | REVISED SCHEDULE |
Bid Submission |
06 November 2015 12 Noon |
11 November 2015 12 Noon |
Bid Opening |
06 November 2015 3 PM |
11 November 2015 1 PM |
After considering the queries, clarifications, recommendations and suggestions, the BAC4IGOV hereby decides to include, revise, amend, delete and/or adapt the following provisions:
Original Provision | Amended Provision | |
Technical Specifications | ||
Lot 1:
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic cable in Baguio City |
||
E. Contractors must submit the following during post qualification: | E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB. | |
Lot 2:
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City |
||
II. Scope of work | ||
1. Laying of FOC cables (96 and 48 cores) at Baguio approximately twenty (20) kms with Thirty Four (34) agencies to be connected. | 1. Laying of FOC cables (96 and 48 cores) at LEGAZPI approximately twenty (20) kms with Thirty Four (34) agencies to be connected. | |
F. Contractors must submit the following during post qualification: | F. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB. | |
Lot 3:
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Palo Leyte |
||
K. MAINTENANCE OF FOC NETWORK IN REGIONAL GOVERNMENT CENTER IN LEGAZPI CITY FOR TWO (2) YEARS | B. MAINTENANCE OF FOC NETWORK IN REGIONAL GOVERNMENT CENTER IN LEGAZPI CITY FOR TWO (2) YEARS | |
L. FIBER OPTIC CABLE SPECIFICATIONS | C. FIBER OPTIC CABLE SPECIFICATIONS | |
M. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS | D. HANDLING AND STORAGE OF FIBER OPTIC CABLES, EQUIPMENT, FACILITIES AND MATERIALS | |
N. Contractors must submit the following NOT MORE THAN THREE (3) DAYS AFTER THE DECLARATION OF lcb OR scb: | E. CONTRACTORS MUST PRESENT THE FOLLOWING NOT MORE THAN THREE (3) CALENDAR DAYS AFTER RECEIPT OF NOTICE FROM THE BAC4IGOV THAT THE BIDDER HAS BEEN DECLARED L/SCB | |
Annex V-A Technical Bid Form page 3 of 5 |
||
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP). | Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP). | |
Annex V-B Technical Bid Form page 3 of 5 |
||
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP). | Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP). | |
Annex V-C Technical Bid Form page 3 of 5 |
||
Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred twenty (120) calendar days from date of receipt of Notice to Proceed (NTP). | Detailed work plan, including milestones and critical tasks, in implementing the project within the allotted one hundred eighty (180) calendar days from date of receipt of Notice to Proceed (NTP). |
Lot 2:
Design, Supply, Delivery, Installation, Splicing, Testing Commissioning, Operation and Maintenance of Brand New Fiber Optic Cable in Legazpi City |
|||||||||
Revised Annex VIII-B1 Revised Detailed Financial Breakdown Page 1 of 4 |
|||||||||
No Stipulation |
|
||||||||
Revised Annex VIII-B1 Revised Detailed Financial Breakdown Page 2 of 4 |
|||||||||
No Stipulation | Design, Supply, Delivery, Installation, Splicing, Testing, Commissioning of Brand New Fiber Optic Cable Network in Legazpi
|
Please use the following forms attached in this Supplemental Bid Bulletin:
- Revised Technical Specifications as of 03 November 2015
- Revised Annex V-A as of 03 November 2015
- Revised Annex V-B as of 03 November 2015
- Revised Annex V-C as of 03 November 2015
- Revised Annex VIII-B1 as of 03 November 2015
- Revised Checklist for Bidders as of 03 November 2015
To download this bidding document, click on the link below:
For information and guidance of all concerned.
(SGD.) DENIS F. VILLORENTE
Chairman, BAC4IGOV